The
role of economic
and performance analysis in
process re-engineering
Here is a way to ensure that process re-engineering
will produce positive bottom-line benefits in terms of customer service,
employee behavior, cycle-time reduction, and cost savings.
by Paul A. Sharman
Thousands of organizations have attempted to use process
re-engineering techniques during the past five years, but many applications are considered
to be failures. This is often the case because of unrealistic expectations, inadequate
analysis, and a lack of understanding about human behavior.
Two years ago a Business Week magazine article chronicled
the woes of consultants Hammer and Champy as they blamed middle management for the failure
of process re-engineering. The argument in the article implied that it was not the fault
of the consultants who were responsible for providing advice to management. But, shouldn't
the consultants have anticipated the problems? What they lacked was an adequate
measurement framework with which to plan re-engineering work, and monitor implementation,
performance, and results.
Measure performance to
manage performance
On occasion, I have been asked to evaluate the benefits of
planned process re-engineering projects, where the design work is complete, but
initiatives are not yet fully implemented. One recent example of this serves to illustrate
the theme of this article. It relates to a company that had a team of employees working
for a year to re-engineer what had been identified as "the critical process." It
was called the "order-to-cash process," which began with customer-order
generation, and ended with cash being received. Expected re-engineering benefits included
improvements in cycle time, accuracy of order fulfillment, consistent on-time performance,
and substantial savings. Management's goal was to reduce division payroll cost by 20 per
cent. This expectation was based on an analysis of strategy that was used to identify the
critical process. It appeared reasonable to everyone that because the "order-to-cash
process" was the critical process, then, by definition, it was the one that consumed
the vast majority of resources employed by the company.
In spite of this perceived logic, the vice-president
responsible for the project, who was a canny numbers person, made this request of the
team. "Before I approve implementation of your re-engineering recommendations, prove
to me that we will achieve the cost-improvement goals."
"Well," the team members sputtered, "we
didn't do any analysis of costs. But we know from our process maps that the identified
critical process touches every major department -- the changes we have suggested are
significant, and so it follows that cost will reduce."
The team members knew that to determine the cost benefit of
their recommendations would be difficult, subjective, time consuming, and maybe costly. It
would certainly require them to go over stuff they had already covered and were already
convinced about, and, moreover, they felt it would be boring. After all, the interesting
work would be implementation!
Fortunately, the VP prevailed. She instructed the team to
hold off while the corporate controller conducted an economic analysis to determine the
costs and benefits of recommended process changes.
The controller knew that, to determine the cost of the
process, he would have to calculate the cost of the resources consumed by that process.
Because steps in the process were performed in virtually every department, a question was
raised on wheth er asking people how much time they spent working on the process, would be
adequate. "Will we reconcile to the books?" asked
The availability of verifiable
numbers-based facts changed the emphasis from process
re-engineering to measuring and managing processes and performance.
the controller, and, "How will people know when they
are spending time working on this process versus others? What about the other things they
do, like administration, training, attending meetings and supervising staff? Most people
perform all sorts of activities."
After some consideration of these matters, it was decided
to undertake a complete analysis of all of the activities that were performed in all of
the departments. That way, it could be certain that all activities relating to the
"order-to-cash process" would be accounted for.
Initially, this approach appeared to be overwhelming,
because the departments involved employed 800 people and incurred expenditures of roughly
$100 million. However, it was perceived that the analysis was sufficiently important to
proceed. Management established a separate team to perform an economic analysis of the
process, using activity-based costing principles. This independent approach ensured that
the progress of the initial process-analysis team would not be hampered.
The economic-analysis group comprised a cross-functional
team of eight employees. They conducted a series of interviews with selected personnel
from each department, which involved less than 10 per cent of the company's employees,
overall. During the interviews, department employees were asked to speak on behalf of all
of the employees in their immediate section. Department managers were given advance
warning so that they could ensure informed people were involved, and so that these people
might come prepared.
Information was gathered on what activities were performed
by department staff members; the percentage of their time each activity consumed; what
activity drivers were involved, and what caused activities to consume so many resources
(cost-driver analysis). Finally, information on non-financial measures was gathered on
quality and cycle time for each activity. Interviews were completed within six weeks of
initiating the process. During the interview period, team members met each week to review
each others' progress and to validate results.
The economic analysis team included a member of the
controller's staff, whose role was to build a computer model of the activity information,
receive information about activities performed by departments, and assign the cost of the
resources consumed to the activities. As information was received from the interviews,
data was entered into the computer software. Within two weeks of completing the activity
analysis, costs were calculated for every activity in every department.
The process re-engineering team had previously conducted an
analysis to identify all of the processes employed in the organization, in addition to the
"order-to-cash process."The outcome of this effort was a complete list of
significant cross-functional processes with which the organization got work done. The
list, described as a process inventory, included information on the names of processes,
inputs, outputs, definitions, and a few other items. When the activity analysis was
complete, two meetings were conducted between the economic-analysis team and the
process-analysis team.
During the first meeting, team members reviewed the list of
activities performed by each department, and made a decision for each activity as to which
process, or group of processes, the activity contributed to. This analysis took less than
a day to conduct, and was performed this quickly because team members were each
experienced, respected employees, with good communications skills. Among them, they also
had a thorough understanding of activities and processes. When all the activities had been
assigned to processes, process costs, and activity-detail-by-process, could be calculated.
The second meeting involved a smaller subset of each of the
two teams to
review process re-engineering recommendations, and determine the cost impact of each. This
was accomplished by knowledgeable team members reviewing the recommendations to determine
which activities would be affected by any proposed changes. Knowing which activities were
affected, team members were then asked to assess what impact the recommendation would have
on the resources employed by the activity. Would the resources consumed within the process
increase, stay the same, or decrease as a result of the recommendation? They were also
asked to determine the impact on cycle time and quality performance of the process. The
team also assessed roughly what investment would be required to accomplish the change.
Finally, the team was asked to assess the impact of the recommendation on other processes
in the organization.
The outcome of this analysis was a set of economic results
that surprised everyone:
1. Cost of resources consumed by the "order-to-cash
process" would be reduced as a result of re-engineering efforts, by 25-35 per cent.
Good news!
2. Overall cycle time and quality performance for the
"order-to-cash process" would improve substantially. Good news!
3. Contrary to original expectations, overall, the cost of
the "order-to-cash process" was only 19 per cent of the total cost of the
corporation. Therefore, it was impossible to meet the goal of freeing up 20 per cent of
corporate resources by re-engineering this "critical process." Despite the fact
that all but one small department "touched" the process, the departments were
all performing many more activities in support of other processes. The problem was that no
one had made the effort to analyse activities before, and, as a result, incorrect
assumptions had been made. Bad news!
4. Twenty-five per cent of resources employed by the
organization were considered to be used in order to sustain the business.
Business-sustaining activities are ones that have no immediate impact on the performance
of the operating processes, but are somewhat discretionary for management. Bad news, if
the primary objective was cost reduction. Management might have had better results if it
had chosen to reduce the costs of business-sustaining activities.
5. Work displaced by the "order-to-cash process"
improvement recommendations migrated to other processes, and actually caused their costs
to increase. Costs increased less in other processes than the reduction in cost in the
"order-to-cash process," therefore, there was a net saving for the corporation.
While these net savings ended up at about 15 per cent of the "order-to-cash
process," it only amounted to three per cent of total organization cost --
substantially short of the expected 20 per cent. Bad news!
The vice president in charge of the project was quite
surprised by the results of the analysis. While they were not at all what she was
expecting, she was glad that she had insisted on the undertaking. It was clear to her that
she now had facts with which to make balanced decisions and evaluate performance. The VP
instructed the process re-engineering team to proceed with the implementation of its
recommendations. She said, "It is clear that the 'order-to-cash process' is critical
to our future
The challenge for management accountants
is to integrate financial and non-financial measurements into a logical structure that
works as a complete mechanism.
performance, and we must get it right. That it won't
deliver the cost savings we were hoping for, is less important than being assured, with
the facts provided by calculating the cost of activities and of all processes, that we now
know, with relative certainty, where the opportunities lie! We can now prioritize our
actions and assign our people to improvement teams in a way that will maximize the benefit
derived from the efforts of each team." She had one more concern. "How will we
track actual performance on a continuous and current basis so that we will know whether
our actions are accomplishing what we expected?"
In response, the teams recommended that the economic and
measurement analysis be maintained and updated on a quarterly basis so that, as
improvement recommendations were implemented, management could track whether it had
delivered what was promised. Affected operating managers would have to participate in the
approval cycle prior to implementation of improvement recommendations, so that they could
sign up for the actions that they would then be held accountable for. The measurement
system would facilitate evaluation of their performance. The availability of verifiable
numbers-based facts provided relief to everyone!
As a result, the emphasis was changed from process
re-engineering to measuring and managing processes and performance. It was decided that to
re-engineer a process, when it was performing poorly, was a legitimate process-management
option.
Another significant lesson for the company was that, had
the economic and performance analysis been completed before the re-engineering work was
launched, management would have established a completely different set of expectations.
Perhaps the focus would have been on a different process to re-engineer in the first
place. Management might have handled the business sustaining costs first, or may have
chosen to stop some the dozens of other "team-based" projects, and focused
people into a few critical processes.
Role of management accountants
Management accountants own the critical measurement process
in every organization -- the "financial performance measurement process."
Financial performance is used as an aggregate planning and tracking mechanism for money.
The opportunity, as many organizations are finding out, is to integrate the money
measurement system into operational measurement systems. The market is afloat with new
measurement theories, such as the Balanced Scorecard or Control Panels. The challenge
faced in all of these initiatives is to integrate financial and non-financial measurements
into a logical structure that works as a complete mechanism. This is a strategically
important role for management accountants. All of our organizations need integrated
numbers-based facts -- and management accountants are well positioned to deliver them. cma
Paul Sharman, features editor for CMA magazine,
is president of Focused Management Information, an Oakville, Ontario-based company that
helps organizations implement new cost-management techniques. |